Main Street Improvement Project Overview

  • CBCL Commenced Plan
    • January 2013
  • Design Charrette Week and Public Presentation of Plan
    • February 25 – March 1, 2013
  • Main Street Improvement Plan Adopted by Council
    • July 16, 2013
  • Formation of the Main Street Advisory Group
    • August 14, 2014
  • Correspondence Sent to Main Street Businesses Pertaining to Formation of the BIA
    • September 22 and October 29, 2014
  • Town of Conception Bay South and the Main Street Advisory Group Focus Session
    • October 23, 2014
  • Deadline for Objections to the Formation of the BIA (0 received)
    • December 3, 2014
  • Main Street Business Improvement Area Regulation Tabled and Adopted by Council
    • December 16, 2014
  • Regulation Sent to Municipal Affairs (Now Part of Legislation)
    • December 29, 2014
  • BIA Board of Management Nomination Package Sent to Main Street Businesses
    • January 8, 2015
  • Deadline for nominations to the BIA Board of Management
    • February 16, 2015
  • BIA Board of Management Approved and Appointed by Council Following the Nomination Process
    • March 3, 2015
  • Inaugural meeting of BIA Board of Management
    • March 12, 2015
  • Strategic Planning Session Held by BIA Board
    • April 29, 2015
  • Main Street BIA Member Breakfast
    • September 10, 2015
  • Construction Commences on T’Railway Loop (Phase I)
    • September 19, 2016
  • 2nd Annual Main Street BIA Member Breakfast
    • September 22, 2016
  • Official Ribbon-Cutting for T’Railway Loop (Phase I)
    • November 24, 2016

If you have any questions, comments, or concerns, please don’t hesitate to contact Jennifer Lake at 709-834-6500 Ext. 702 or .